M4 EMU PLAINS

At the foot of the Blue Mountains.
Four colour horizontal design painted with anti graffiti.

M4 OLYMPIC WALL

This wall was completed prior to The 2000 Olympic Games on the M4 at Homebush.
The feature bays were rendered prior to large olympic figurines being hand painted onto wall. 

M4 GLENMORE PARK EAST

This Hebel Noise Wall had feature bays specified to incorporate the surrounding topography.
The large feature bays were rendered prior to applying the hand painted feature bay.  

TEXTURE COATING

Most Hebel Noise Barrier Walls have a fine texture applied to create a uniform finish to the wall.

PRIOR TO HOUSING

Noise walls are erected and coated prior to housing developements moving in.

ON SITE PROFILING

Stywill Texture Coating can also profile designs into the Hebel panels as we did here at Punchbowl

RESULT

Our on-site profiling was only part of the overall affect the client was after.
This very unique wall.

HUME HIGHWAY

This wall at Liverpool was very labour intensive with multi colours used.
The project included 'Tree' feature bays and 'Squares' sprayed with a Granite stone finish.

NOISE ABATEMENT

Noise walls are erected to keep industrial impact noise away from residential living and using colours that are easy on the eye.

TUGUN BYPASS

Tugun Bypass job took us interstate to Queensland to rectify Hebel walls coated by in-experienced applicators. We rectified 13,000m2 of Hebel Noise wall. This is what the walls looked like before we arrived. 

Tugun Bypass

        This is  after our rectification. Everyone happy   

TUGUN BYPASS

Work undertaken by STC was carried out on 'live' roads which required us to work at night.
At night everything HAS to work!

TUGUN BYPASS

This high profile job was completed before time and did not affect other trades trying to complete their works which is a credit to STC's employees and contractors on the site. 

RAYMOND TERRACE BYPASS

This project was completed in record time (11,000m2 in 18 days).
Two-tone horizontal colour scheme with contrasting 'Areoplane' features at designated areas of wall. 

RAYMOND TERRACE

The areoplane designs were painted on the residence side of wall just to remind them there are planes screaming around from Williamtown Air Base! 

BELLA VISTA

We also texture coat 'Estate' and retaining walls designed by Tradewest P/L.  
Estate walls are constructed with 300mm Hebel panels and coated with a fine spray-on texture called Finesse supplied by Duramax.

ALFORDS POINT RD

One kilometre long wall with a 25mmx12mm 'Wave Line' routed into the Hebel panels for the entire length of wall.
Painted a contrasting blue colour. 

M5 MOTORWAY

First road project undertaken by Stywill Texture Coating P/L consisting of 80,000m2 of Hebel Noise Walls, 1990. 

M2 MOTORWAY

Access to anywhere. M2 motorway 155,000m2 Hebel Noise Walls.
A lot of access problems had to be overcome. 1996.

M2 MOTORWAY

We mean access to anywhere! 

BANGOR BYPASS

Bangor Bypass
40,000m2 - Paint only

Hebel Noise Barrier Walls

BANGOR BYPASS


Minimal impact on the enviroment. 

Epping to Thornleigh Third Track.      

   STC completed 13,00m2 of Hebel Noise Wall on the ETTT. in 2016                                  

ETTT

The project brought up some interesting access challengers, which were all overcome. 


ETTT               

There were some access problems on the residence side too!

Using Format